Project Update - August 2023

Installation of continuous disinfecting dosing systems at Baradine, Binnaway and Coonabarabran Pools is well underway. Pouring of concrete pads for tanks is complete. The contractor to complete electrical upgrades to pools at Baradine, Binnaway, Coonabarabran and Dunedoo Pools has been engaged and works are complete at Binnaway. Plant and equipment improvements have commenced with pump servicing and assessments underway.

Last Updated: 19 Sep 2023