Project Update - February - March 2022

February - March 2022

Bricklaying, and co-related trades work such as electrical work and plumbing, and some structural steel frame components, required within the walls, was done over the six weeks spanning late January to early March. With the completion of bricklaying in the second week of March, other subsequent trades work can now continue: external sewer plumbing and sewage pump station, together with external stormwater lines. Structural roof framing and roofing will also be done in March. Internally, items such as waterproofing and tiling, and electrical, will also commence.

The project is due for completion in late April.

The following photos show the current status of the Project.

 
87-2022 Robertson Oval Amenities Building - 10-03-2022 image 4

 

87-2022 Robertson Oval Amenities Building - 10-03-2022 image 1

87-2022 Robertson Oval Amenities Building - 10-03-2022 image 2

87-2022 Robertson Oval Amenities Building - 10-03-2022 image 5

Image: Glulam beams now in place for roof structure