Rain has been an issue affecting progress on this Project over the last month or so, however the contractor has timed things well to work between rain events. The work done includes the stripping of the formwork from the main slab, set out for the next stages of the project, and installation of some site services. The main activity of note has been commencement of bricklaying for the new walls. This photo shows a few of the internal walls being done. Following brickwork, the next item will be the framework for the roof.