Project Update - April 2022

Works that have been completed over the last month at Robertson Oval includes:
• External sewer lines and installation of Sewage Pump Station
• Underground external stormwater lines
• Roof framing and glulam beams
• Insulated roof panelling.
• Wet areas waterproofing 
• Internal electrical wiring in readiness for distribution board
• Preparation work including earthworks for concrete footpaths
• Preparation work for storage shed concrete slab.

Work that are still continuing and yet to be completed include tiling, internal fitout, PC items, landscaping and storage shed.

The project is anticipated to be completed by the end of the month.