Council crews are working on the section of Purlewaugh Road between Darouble Road and Purlewaugh. Council has completed the eastbound shoulder and has also completed approximately 50% of the westbound shoulder. The contractors work has been finalised. The project is scheduled to be completed by the end of May.
Last Updated: 16 Jun 2023