Project update - March 2023

The contractor has returned to site, and will be doing minor repairs to the pavement over the next 4 days. Traffic control flagmen will be closing part of the road as necessary for the works.

Council crews are working on the section between Darouble Road and Purlewaugh. The eastbound shoulder has been completed and sealing works have been scheduled for the week commencing 27 March 2023. Work will begin on the westbound shoulder after Easter.

Photo: New pipe installed on section 8 of Purlewaugh Road.

20230323 Purlewaugh Road Upgrade