Council has engaged a local contractor to construct Stage 1 of the shared pathway in Lachlan Street, Baradine.

The project is to construct a 2.5m width x 100mm thick concrete footpath, 150mm above the road level to accommodate any future kerb and gutter. The project is expected to start at the end of April 2023. Adjoining residents will be notified two weeks prior to the works commencing.

 

Last Updated: 24 Jun 2023