Construction works on the Baradine Skate Park commenced on Tuesday 3 March 2020.

CONVIC have now carried out earthworks on the site, and concreting works have now commenced with the first pour being completed on 13 March and the 2nd pour scheduled for 14 March.

The programmed completion date for this project is 29 April 2020, and at present works are proceeding according to schedule.