Works and Projects Update

Updates on projects, road, park and maintenance works happening across the Warrumbungle Shire.

Works are subject to weather conditions. Please plan your travel accordingly and allow extra time when works are taking place.

Week commencing 29 June 2026

The following works will be undertaken across the Shire weather permitting. Please drive with care around work zones and allow extra travel time.

Maintenance Grading

Yarragrin Rd, Mendooran

Three Hills Rd, Coonabarabran

Pandora Pass Rd, Coolah

Fairfield Rd, Dunedoo

RMCC Work - Shoulder Works and Drainage

Coonabarabran Rd

Patching

Purlewaugh Rd, Coonabarabran to Premer

Premer / Tambar Springs Rd, Premer to Shire Boundary

Vinegaroy Rd, Coolah to Shire Boundary

Coonabarabran Rd

Castlereagh Highway

Golden Highway

Newell Highway

Slashing

Gwabegar Rd, Baradine to Shire Boundary

Baradine Goorianawa Rd, Baradine to Bugaldie

Sign Maintenance

Baradine Rd, Coonabarabran to Baradine

Coonamble Rd, Baradine to Shire Boundary

Gwabegar Rd, Baradine to Shire Boundary

Forest Rd, Mendooran to Shire Boundary

Warrumbungles Way, Coonabarabran to Black Stump Way Intersection

 

To report an issue please visit Contact Council | Warrumbungle Shire Council or phone Council on 02 6849 2000.

Week commencing 9 June 2026

Warrumbungle Shire Council is keeping our community informed with regular updates on works on roads and recreation and community spaces across the Shire.

ROADS

The following works will be undertaken across the Shire in the next week. Please drive with care around work zones and allow extra travel time.

Grading

Old Common Rd, Coonabarabran 

Dandry Rd, Coonabarabran

Mendooran Rd, Mendooran

Patching

Baradine Rd, Baradine

Coonabarabran Rd, All segments

Castlereagh Highway, All segments

Golden Highway, All segments

Newell Highway, All segments

Resheeting

Minnedah Rd, Tannabar

Banoon Rd, Coolah

Shoulder Grading

Warrumbungles Way, Binnaway

Golden Highway, Uarbry

Slashing

Goolhi area

Sign Maintenance

Bugaldie Goorianawa Rd, Bugaldie

Indian Lane, Kenebri

Coolah town streets

 

PROJECTS

There’s plenty happening across our local roads, parks, playgrounds and recreation spaces. Below are the latest updates on current projects.

AGRN 1034 Natural Disaster Culvert Restoration Works

Cumbil Road (Johns Crossing): Bridge works construction is expected to commence in July 2026.

Burragundy Road: The tender for the design and construction has been advertised and is closing 9 June 2026.

Sandy Creek Road: Box culvert works commenced on 25 February 2026 with kerbs remaining to be poured and scour rock placement. Sandy Creek Road is expected to be open to traffic on 30 June 2026.

Rotherwood Road: Box culvert construction commenced on 1 May 2026. The base slab and the two blade walls poured have been poured with the remaining two expected to be poured this week weather permitting. The project is targeted for completion by July 2026.

COMMUNITY PROJECTS

BARADINE

Baradine Oval Kiosk Awning Structure and Accessible Toilet: Site works and the final building certifier inspection have been completed. The Occupation Certificate has been lodged and is currently being assessed.

COOLAH

Bowen Oval New Amenities Building: Site works have been completed, site demobilisation and the inspection by the building certifier are underway.

School of Arts: Repairs to parapet wall above the roof and concrete ball project continues, but is currently delayed due to weather.  Footpath travel maybe rerouted during the project.

COONABARABRAN

Native Grove Cemetery Expansion: With the irrigation works completed last week, turfing and final tidy-up works are planned for this week, leading to completion of the project.

Coonabarabran Footpath Project: With the tree planting now completed, two seats along the footpath are being ordered for installation, which is the final element of the project.

GOOLHI

Goolhi Hall: Installation of the new water tank and plumbing have been completed. The minor kitchen renewal works will be completed by mid-June 2026.

MENDOORAN

Mechanics Hall Kitchen: Renewal is nearing completion. The final item remaining is delivery of the new stainless steel refrigerator.

 

Week commencing 25 May 2026

Warrumbungle Shire Council is keeping our community informed with regular updates on works on roads and recreation and community spaces across the Shire.

ROAD WORKS AND MAINTENANCE

The following works will be undertaken across the Shire. Please drive with care around work zones and allow extra travel time.

Grading

Warkton Road, Tannabar

Mendooran Rd, Mendooran

Pindari Rd, Coolah

Patching

Forest Rd, All segments

Tooraweenah Rd, Mendooran

Mendooran Rd, Mendooran

Coonabarabran Rd, All segments

Castlereagh Highway, All segments

Golden Highway, All segments

Newell Highway, All segments

Timor Rd, Coonabarabran

Coonabarabran town streets

Piambra Rd, Binnaway

Merrygoen Rd, Merrygoen

Resheeting

Bingie Grumble Rd, Tannabar

Banoon Rd, Coolah

Pindari Rd, Coolah

Shoulder Grading

Warrumbungles Way, Binnaway

Golden Highway, Uarbry

Slashing

Goolhi area

Sign Maintenance

Binnaway Rd and town streets

Coolah Rd and town streets

Vinegaroy Rd, Coolah

PROJECTS

There’s plenty happening across our local parks, playgrounds and recreation spaces.

AGRN 1034 Natural Disaster Culvert Restoration Works

Cumbil Road (Johns Crossing): Bridge works construction is expected to commence in July 2026.

Burragundy Road: The tender for the design and construction has been advertised and is closing 9 June 2026.

Sandy Creek Road: Box culvert works commenced on 25 February 2026, with kerbs remaining to poured and scour rock placement still to be completed. Sandy Creek Road is expected to open for traffic on 30 June 2026.

Rotherwood Road: Box culvert construction commenced on 1 May 2026.The fish passage has been constructed with the base slab being poured this week. The project is targeted for completion by July 2026.

COMMUNITY PROJECTS

BARADINE

Baradine Oval Kiosk Awning Structure and Accessible Toilet: 95% complete. The final lock installation for the accessible toilet and final inspection for the Occupation Certificate are scheduled for next week.

Oxley Crossing Picnic Table: This project is complete with the covered picnic table and rubbish bin installed.

COOLAH

Bowen Oval New Amenities Building: With all internal services installations completed, the installation of toilet fittings and final finishes is in progress. Expected completion is within 2 weeks. The external footpath and parking works have also been completed.

School of Arts: Repairs to parapet wall above the roof and concrete ball project has commenced. Footpath travel maybe rerouted during the project.

COONABARABRAN

Coonabarabran Footpath Project: With the tree planting now completed, two seats along the footpath are being ordered for installation, which is the final element of the project.

Native Grove Cemetery Expansion: Irrigation works are scheduled for next week, while turf placement is expected to be completed by the first week of June.

GOOLHI

Goolhi Hall: Installation of the new water tank and plumbing have been completed. The minor kitchen renewal works will be completed by mid-June 2026.

MENDOORAN

Mechanics Hall Kitchen: Renewal is nearing completion. The air conditioning is being installed and staff are awaiting delivery of the new stainless steel refrigerator.