Council’s contractor, Forpark Australia have completed the installation of the playground equipment on 21 January 2022. The installation work was delayed due to wet weather in December and latent conditions.

Council’s contractor for shade sails, Central Industries have completed the installation of the shade sails on 2 February 2022.

The volunteers organised by the Park Management Committee have completed the installation of fence posts where the fence crosses the softfall.

The softfall installation is programmed to commence on 7 March 2022. This was delayed from 31 January due to staff shortages and wet weather.

 