Council’s Contractor D&C Powerline Constructions has submitted their design to Essential Energy. The design approval process can take up to 12 weeks. The Contractor will have to give Essential Energy at least four (4) weeks’ notice of the works because it will involve a planned power outage. A total of six (6) weeks will be required to complete the site works after design approval.