Council’s Contractor, Forpark Australia has completed the installation of the playground equipment on 21 January 2022. The installation work was delayed due to wet weather in December and latent conditions.

Council’s Contractor for shade sails, Central Industries has completed the installation of the posts on 14 January 2022.

The volunteers organised by the Park Management Committee have completed the installation of fence posts where the fence will go across the soft fall.

The soft fall installation is programmed for 31 January 2022.

 