Council has provided the owner’s consent form and easement documents to Essential Energy (EE) on 9 Aug 2022. EE will have to give approval for the easement and design. Once approved, the contractor D&C Powerline Constructions will have to give Essential Energy at least 4 weeks’ notice of the works because it will involve a planned power outage. A total of six (6) weeks will be required to complete the site works after design approval.