Project Update - December 2021

The Contractor for this project, Oasis Skate Parks, have completed all the concrete works in accordance with the agreed design plan. The skate park structure is 100 % completed, however landscaping works are yet to be completed. Without the landscaping works, the skate park is not safe to be opened to public. Hence, Council have fenced off the site to ensure public safety. The landscaping works are programmed to be completed in January 2022, weather permitting.

Council requests that eager skate board riders be a bit more patient until the facility is 100% complete and open to public.

  