Project Updates

Week to 5 July 2018

Works at the Coonabarabran Multipurpose Courts have continued this week with formwork, steel mesh and plastic membrane being put in place and expansion joints being installed. Footings for the goal posts have been poured and final preparations are taking place for the concrete pour for the courts.  It is expected that the concrete pour will commence on Monday, 9 July 2018, and will continue for around five (5) days with a total of 445 cubic metres of concreate being poured.

Ready for Concrete Pour - 5 July

 Image: Courts prepared for the concrete pour

Steel Mesh and Plastic Membrane - 5 July

Image: Steel mesh and plastic membrane in place

Preparing construction Joints - 5 July

Image: Preparing construction joint courts