Works on the multipurpose courts in Coonabarabran have been progressing well again this week. The concrete pour has now been completed on all five (5) courts. The concrete will now need to be cured for 10 days before the joints are sealed. Surfacing of the courts has been scheduled to commence on 20 August 2018.

This coming week the goal posts are being erected. Footing steel and templates for the light towers have arrived on site with plans for these to be in place next week. The electrician has also begun work on the courts this week.