Billy Kings Creek Bridges Construction Project

Work has advanced well on site this week at Billy Kings Creek on Purlewaugh Road, Coonabarabran. Bridge 1 abutments have the steel in place and formwork installation is in progress for a concrete pour on Monday, 23 March 2020. Bridge 2 preparations for piling have been completed and will now allow pile driving to start. Construction works are approximately 2 weeks ahead of the programmed schedule.

Social Media - Billy Kings Creek Bridges Project Photo - 13-03-2020

Photo – Billy Kings Creek Bridge No 1 abutments have the steel in place

Last Updated: 17 Mar 2020