Week to 6 June 2018

Works are well under way with the earthworks nearing 75% completion. Excavation works have now been completed and all fill material has now been delivered and spread. This week earthworks are at the final level of spreading the fill material for the whole site. Compacting and trimming of this surface will commence this week to provide footing for the new concrete surface to be poured in July. The multipurpose goal posts and luminaries have been delivered and are being stored ready for installation once the final surface has been poured and matured.

Earthworks 1 - 6 June 

Image: Earthworks are nearing final level

Earth Works Trimming - 6 June

Image: Trimming and compacting the earthworks.

Eather Works Compacting - 6 June

Image: Compaction of the earthworks layers.