The Coonabarabran Multipurpose Courts are almost complete! The concrete for the courts has now been cured, cleaned and sealed, with painting and line marking underway.

The erection of the light towers and the connection of the electricity is also complete.

All that is remaining is turf, irrigation, traffic barriers and fencing which is all scheduled for the coming weeks.

5 Sep - Court surface cleaning

Image: The court surface crew cleaning the concrete before applying the sealer coat.

5 sep - lighing has been installed

Image: Lighting towers have now been installed. 

5 Sep - Colouring of court

Image: Court colouring has started