Project Update

Week to 20 July 2018

This week, works have continued on the new multipurpose courts being constructed in Coonabarabran with the concrete being completed for all five (5) courts. The concrete is currently under plastic sheeting to be cured for up to 10 days. Once the concrete is cured the plastic sheeting will be removed to allow for the joint sealing to take place.
 
This week the goal posts have also been erected and the steel footings for the lighting towers have been put in place. The concrete pour for the footings for the lighting towers will soon be completed. Electrical cabling has also been placed across the court in preparation for the installation of the lights.

Concrete works and goal posts - 20 July

Image: The concrete works and goal posts are completed.

Light tower footings - 20 July

Image: Light tower footings are being poured.